PSEM NCRReference platform

04

Mining Operations

Drilling, blasting, loading, hauling and ground control across surface and underground methods.

Version
4.1
Last reviewed
2 Aug 2026
Reading time
74 min · 118 pp
Access
Public
Chapter 04 · 4.0 Introduction
0% read
4.0

Introduction

3 min readPublic

Mining operations convert a planned reserve into broken, transported material at a rate and cost that the mine plan assumed. Every unit operation described in this chapter exists to move rock from an in-situ state to a stockpile, crusher or waste dump with the least energy, the least dilution and the least exposure of people to hazard.

The chapter treats surface and underground methods together where the engineering logic is shared, and separately where geometry forces different answers. Readers new to operations should begin with the unit-operation framework in section 4.1 before moving to method-specific material.

4.1

The unit-operation framework

8 min readPublic

Four unit operations recur in almost every mining method: drilling, blasting, loading and hauling. Ground support is treated as a fifth in underground contexts and as slope management in open pits. Each operation has an input from the one before it and imposes a constraint on the one after: fragmentation from blasting sets loader dig rates, loader bucket size sets truck body geometry, and truck cycle time sets the fleet that a schedule can rely on.

Because these operations are coupled, optimising one in isolation is usually a mistake. A coarser fragmentation target saves explosive but costs crushing energy; a shorter haul saves fuel but may require a steeper ramp that raises tyre wear and rollover risk. Operations engineers work at the interfaces.

Table 4.1 in the reference material summarises typical productivity ranges by equipment class. Treat them as order-of-magnitude checks rather than design inputs; site conditions dominate.

4.2

Open-pit methods

14 min readPublic

Open-pit mining removes overburden and ore in a sequence of horizontal benches. Bench height is fixed early by the drill and loading equipment selected, and is typically between 10 and 15 metres for large operations. Berm width, batter angle and bench height together fix the inter-ramp slope angle, which geotechnical analysis then confirms or constrains.

Haul roads are the most under-designed element of many pits. Grade should not exceed 10 percent on sustained ramps, running surface width should be at least three and a half times the widest vehicle for two-way traffic, and drainage must be designed rather than assumed. Poor roads show up first in tyre cost and later in incident statistics.

Phase design divides the ultimate pit into pushbacks that balance stripping ratio through the life of mine. The practical constraint is minimum mining width: a phase too narrow for equipment to work efficiently will be mined late, slowly and expensively.

4.3

Underground methods

16 min readPublic

Underground methods are chosen by orebody geometry, rock mass quality and grade. Room-and-pillar suits flat, tabular deposits in competent rock. Sublevel open stoping and its long-hole variants dominate steeply dipping, moderate-width orebodies. Cut-and-fill and drift-and-fill accept weaker ground and irregular shapes at the cost of cycle time. Block and panel caving trade selectivity for very low unit cost in large, low-grade, cavable rock masses.

Development precedes production and rarely keeps pace with it. Decline gradient, cross-sectional area and ground-support standards fix advance rates; a mine that under-invests in development in year two will be short of stopes in year four.

4.4

Drilling and blasting

12 min readMembers

Blast design starts from the required fragmentation and works backward to hole diameter, burden, spacing, stemming and timing. Powder factor is a result, not a target. For most production blasting in competent rock, burden is about 25 to 35 hole diameters and spacing 1.1 to 1.3 times the burden.

The rest of this section is for members.

Sign in to continue reading, or request membership access.

4.5

Loading and hauling

11 min readMembers

Loader and truck matching aims for three to five passes per truck. Fewer passes waste loader capacity; more passes leave trucks queuing. Cycle time is estimated from segment distance, grade and rolling resistance using rimpull curves, then corrected for operator and site factors that can easily add 20 percent.

The rest of this section is for members.

Sign in to continue reading, or request membership access.

4.6

Ground control

10 min readMembers

Ground control is the engineering of excavations so that they remain stable for as long as they are needed. In open pits this means slope design, dewatering and monitoring with radar and prisms. Underground it means support standards by ground class, scaling and inspection routines, and a trigger action response plan that tells every person what to do when instruments or observations exceed limits.

The rest of this section is for members.

Sign in to continue reading, or request membership access.